ALL PROCESSES AND STEPS
NEEDED IN CONSTRUCTION OF A NEW HOME (RESIDENTIAL HOUSE)
In building
a new HOME or Construction of residential building the following preliminary paper
works are needed before commencing or embarking on the actual construction.
These
processes/steps include;
·
PREPARATION OF WORKING DRAWINGS
as required by the client (End user or Direct owner).
Working drawings cover the plot layout, floor and roof plans,
elevations or views, sections, kitchen/toilet detailing, etc. An Architect is
responsible for the drawings.
Also, structural drawings are prepared by a Civil Engineer if
necessary, especially when the proposed HOME/building is more than one floor,
or to be sited in a poor soil. Please consult a Structural Engineer for a
proper design. HOMES should be safe.
·
BUILDING COST ESTIMATION.
Estimation of material cost, labor cost and unforeseen contingencies comes
next. This is professionally carried out by a Quantity Surveyor (Q.S) using a
current and standard format of BOQ or BEME because cost of materials and labor
varies with time and location. Proper estimate should be provided to the client
so as to know how financially buoyant he/she is to fund the project execute.
Cost should be affordable.
·
APPROVAL OF DRAWINGS AND
COST ESTIMATES FROM CLIENT. The client must go through the documents (drawings
and bills) submitted by the contractor and make an approval if it’s ok by
him/her without any corrections or adjustment.
·
DRAWING APPROVALS FROM TOWN
DEVELOPMENT AUTHORITY. This is very necessary when building a new HOME in the
urban locations with a master plan, It is important because both residential
and commercial building drawings must meet up the authority’s slated
regulation. The Physical Planning units, Building Control Agencies, etc review
the submitted drawings and issue out an approval number.
·
COMMENCE CONSTRUCTION WORK. You
can either go through contractor or hire labor on daily basis. Whichever suits
your budgets and depending on the complexity of the HOME project. I always advice
for a competent, professional and qualified personnel to handle building
projects. It costs more correcting an error rather than avoiding it. Don’t be
too smart.
·
BARRICADING AND MARKING OF
PLOT PERIMETER BOUNDARIES. The site has to be protected from people coming in,
safe for workers thus it has to be barricaded for safety. Mark out boundaries
to know extent of clearing.
·
CLEANING OF SITE. Every
construction site should be cleared out of trees, shrubs, grasses, unwanted and
harmful materials and debris before commencing activities or construction
phases.
·
SETTING OUT/PREPARATION OF
SITE LAYOUT AS SHOWN IN THE DRAWING PLANS. Here, the ground floor or basement
floor plan is transferred to the gound via setting out or pegging. Accuracy is
needed at this level to get the correct positioning, measurements, angles
squared or curvatures.
After the completion of this, the actual construction on plot
begins via the following procedures;
A. EXCAVATION/EARTH WORK
Depending
on the type of foundation to be dug, it could be manually or mechanically
aided. Generally excavation is carried out for the construction of wall
foundations. Excavation should be carried out as per the drawings defined
lengths & widths. After excavation, layout the foundation and backfill the
remaining excavated area around foundation with soil.
Floor
levels of residential buildings are higher than the natural ground level. Fill
the area with soil up to floor levels and compact the soil. Now earth work of
residential building is finished.
B. CONCRETE WORK IN FOUNDATION
Level the
foundation base to same level. It is very necessary to check the levels of foundation
before concrete work to avoid using concrete to fill up excess volume which
will cost much. There are patches where excavated depth slightly exceeds and
vice versa. Now pour the concrete as per drawing specs. Generally concrete of
ratio 1:4:8 is used for foundation. Sometimes it is even 1:5:10 etc.
Here 1:4:8 means;
1 part cement per cubic
4 parts of sand per cubic
8 parts of coarse aggregates
Depth of
foundation varies from 9” to 18” and normally for most of the cases it is
considered as 12’’ depth. Keep foundation width equals to its depth.
C. DAMP PROOF COARSE.
To protect
walls from moisture, a layer of damp proof coarse material is laid down at
floor level. Thickness of this concrete layer is 0f 1 inch. Material of damp
proof coarse layer consists of concrete ratio 1:1.5:3 with a mixture of water
proof material 1kg/bag.
D. MASONRY WORK
Masonry
work is carried out with cement mortar. Cement mortar is a mixture of cement
& sand. Ratio of cement mortar varies from 1:4 to 1:6. Here (1:6) mean, 1
part cement and 6 parts of sand. Dampen about 25 bricks with a hose pipe and
clean away all loose dirt from the top of footing and moisten about a meter of
surface at one end of the foundation with the hose pipe. Throw a mortar line
just behind the threaded level line and lay bricks on the mortar bed. Make sure
bricks exactly follow the threaded horizontal level line
E. LINTEL
Masonry
work of buildings is carried out in one go till roof. Openings for windows
& doors are left during masonry works. Reinforced cement concrete beams are
laid down on the top of openings. So, those loads of structure above openings
not directly come on to the door frames.
F. PARAPET/ROOFING
Parapet are
formed by carpenters and cast reinforced before casting with concrete. Roof
slab of building is poured after completion of masonry works. Now a days,
roofing is of reinforced cement concrete slab. Slab thickness &
reinforcement details should be according to approved drawings.
G. DOORS & WINDOWS
Traditionally,
doors and windows of woods are used. But, steel & aluminum is also not a
bad choice. In case of wooden doors & windows, frames are fixed in walls
during masonry work. Panels are then fixed with hinges after plaster work.
Steel and aluminum doors are fixed after completion of paint work.
H. M & E SERVICES
These are
Electricity supply, gas supply, water supply, sanitary etc. Conduits for
electric supply are fixed in walls before plastering. Every conduit pipes, both
mechanical and electrical must be standard. For hot water pipes, no substandard
is allowed. Similarly water supply and sanitary lines are also laid before
pouring of building floor. Services are very important for every single house.
Different types of services are provided during construction.
Note: Gas lines are not fixed in walls or
slabs. Gas line remains open in air
I. PLASTERING & PaINTING
Form work
is removed after 21 to 28 days of slab pouring. Now plaster work begins. Good
plaster sand must be used and a thorough mortar mix to avoid cracks on
plastered walls. Mortar for plaster work is generally of 1:3 or 1:4 is used.
Thickness of plaster layer should not be more than 0.75inch. Cure the surface
about 7 days. So that, plaster gain proper strength.
Generally,
internal walls of buildings are covered with plastered layer and external walls
with pointing. It is better plaster the external walls rather than pointing
J. FLOOR AND CEILING FINISH. (TILING & POP)
Depending on the type of floor and ceiling finish the client
wants. Floor could be screeding, tiling, carpeting, marble, terrazzo, etc.
ceiling finish could be POP, PVC, Asbestos, suspended ceiling, etc.
K. FURNITURE, INSTALLATIONS AND FITTINGS ARE DONE.